Judge orders Enbridge to remove oil pipeline from Wisconsin tribal land within 3 years, pay $5 million

A federal judge ordered Canadian energy company Enbridge on Friday to remove parts of an oil pipeline on tribal lands in Wisconsin and to pay the tribe more than $5 million for trespassing. 

The ruling came after the Bad River Band of Lake Superior Chippewa sued Enbridge in 2019, claiming the around 12 miles pipeline is in danger of rupturing on their land and that land agreements allowing it to run on the reservation expired in 2013. 

US District Judge William Conley ruled in Madison, Wisconsin, that along with the $5.15 million, Enbridge must pay the tribe a portion of the profits as long as the pipeline remains on the land. 

Conley, however, ruled the pipeline wasn’t in imminent danger of bursting and said an immediate shutdown would “spark at least temporary shortages and increased prices for refined gas, propane and butane in the Upper Midwest and Eastern Canada, creating hardships, specially for the poor and other economically challenged households.”


A federal judge ordered Enbridge to remove parts of its Line 5 pipeline that cross tribal lands in Wisconsin, following a lawsuit.
A federal judge ordered Enbridge to remove parts of its Line 5 pipeline that cross tribal lands in Wisconsin, following a lawsuit.
AP

The tribe had argued that an emergency exists because erosion leaves the Line 5 pipeline at risk of being exposed, which experts have warned in court could weaken the pipeline until it ruptures, causing an oil spill. 

Conley said, “given the environmental risks, the court will order Enbridge to adopt a more conservative shutdown and purge plan,” ordering it to “cease operation of Line 5 on any parcel within the Band’s tribal territory on which defendants lack a valid right of way and to arrange reasonable remediation at those sites.”

He also told Enbridge and the tribe last November to create an emergency shutoff plan. 


A Pipeline used to carry crude oil sits at the Superior, Wis., terminal of Enbridge Energy on June 29, 2018.
A pipeline used to carry crude oil sits at the Superior, Wis., terminal of Enbridge Energy on June 29, 2018.
AP

Enbridge said it plans to appeal the decision, saying it disagrees that it is trespassing on tribal land but added it “remains open to an amicable resolution with the Bad River Band.”

It said a long-term solution is a 41-mile reroute of the pipeline that relies on “timely government permit approvals” for it to be done within three years. 

The pipeline stretches 645 miles across Wisconsin, Michigan and Ontario, carrying 23 million gallons of oil and natural gas each day. 

For all the latest Business News Click Here 

 For the latest news and updates, follow us on Google News

Read original article here

Denial of responsibility! TheDailyCheck is an automatic aggregator around the global media. All the content are available free on Internet. We have just arranged it in one platform for educational purpose only. In each content, the hyperlink to the primary source is specified. All trademarks belong to their rightful owners, all materials to their authors. If you are the owner of the content and do not want us to publish your materials on our website, please contact us by email – [email protected] The content will be deleted within 24 hours.